Dredging and Engineering Works Programme

Dredging small  

Dredging and Engineering Works

The Sediment Management Strategy published by the Broads Authority sets out the known issues and principles for addressing the task of sediment management. The strategy also identifies the volume of sediment that requires removal to achieve ideal waterway specification. This allows the Authority to take a proactive rather than a reactive approach to the dredging of the navigation area.

A hydrographic survey of the waterbodies is compared to the waterways specification, along with disposal opportunities to score and prioritise the sedimenet removal. For further details please see the Sediment Management Strategy.

The 2008/2009 Dredging Programme, detailed below, highlights the Authority's priorities over the comming year.

Works Area Further Details Dates
Dredging                              River Ant                   Downstream of Ludham Bridge Completed 02/2008
Dredging Fleet Dyke Completed 03/2008
Dredging River Bure Horning Church March 2008
Dredging Haddiscoe Reedham - Mid Section Jan 08 - Mar 08
Litter picking New Mills - Bramerton March 2008
Dredging Oulton Broad Bar Dredging Mar 08 - July 08
Dredging River Ant Upstream Ludham Bridge Mar 08 - Nov 08
Earthworks/profiling Jensens Island   May 08 - July 08
Dredging River Thurne/ Heigham Sound Phase 1 Upstream Martham Ferry & Heigham Sound Nov 08 - Feb 09
Dredging River Yare 5 & 7 Mile Bends July 08 - Aug 08
Earthworks Haddiscoe Mud Tip   August 2008
Dredging River Bure Phase 1 Belaugh  Feb 09 - Mar 09
Piling Beccles 24hr Mooring Sept 08 - Oct 08 
Dredging Haddiscoe Cut  St Olaves - Mid Oct 08 - Dec 08
Dredging  Reactive   Jan 09 - Apr 09
       
       
       
       