River Works Programme
Navigation Works Team
The Navigation Works Team maintains and refurbishes our 24 hour moorings, installs signs, clears trees, cuts weed and carries out any other maintenance work close to the waterways to enable you to navigate safely. You can see details of current projects in our works programme.
The team also maintains the navigation rangers' patrol launches and our work boats.
There is a keen group of volunteers who go out with the team and we are always looking for new recruits.
Richard Farley is the Head of Navigation Works, and the team includes:
Richard Bean, Navigation Works Technician
Matt Dane, Navigation Works Technician
Ady Stevens, Navigation Works Technician
Delwyn Delcore, Navigation Works Technician and Assistant Navigation Projects Technician
Keith Perry, Navigation Works Technician and Navigation Ranger
Andy Bartlett, Navigation Works Technician and Navigation Ranger
Robin Allard, Navigation Works Technician and Navigation Ranger
Navigation Works Programme 2008/09
Please note, all the works listed below are subject to change.
| Works | Area | Further Details | Dates |
|---|---|---|---|
| Broads Authority 24 hour moorings | Various locations | Moorings maintenance | 06/2008 & 10/2008 |
| Potter Heigham - Reps Bank | Completed but further work required | ||
| Potter Heigham - Martham Bank | Completed but further work required | ||
| Gay's Staithe 2 | 03/2009 | ||
| St Olaves | Delayed planned April 2009 | ||
| Percys Island | Completed | ||
| Chedgrave Common Returns | Delayed planned April 2009 | ||
| Dilham | Delayed planned June 2009 | ||
| Deep Dyke | Completed | ||
| Deep Go Dyke | Completed | ||
| Thorpe Green Stage 1 | Completed | ||
| Whiteslea Mooring | Completed | ||
| Postwick | 06/2009 | ||
| Rockland Staithe | Footpath | 03/2009 | |
| Paddy's Lane | Footpath | Completed | |
| New moorings | St Benet's Moorings open | 05/2008 | |
| Boundary Farm Stage 2 | Completed | ||
| West Somerton Stage 3 | 07/2008 - 08/2008 | ||
| Hardley Cross Stage 1 | 10/2008 | ||
| Somerleyton | 06/2008 - 07/2008 | ||
| Stalham | 03/2009 | ||
| Polkey's Mill | Fence | Completed | |
| Ladder installations/safety chains | Percys Island | Completed | |
| Cockshute | Completed | ||
| Thurne Mouth | Completed | ||
| Boundary Farm | Completed | ||
| Chedgrave Common | March 2009 | ||
| Wroxham Island | Completed | ||
| Wayford Bridge | 03/2009 | ||
| Paddy's Lane | Completed | ||
| Neatishead | 03/2009 | ||
| Gay's Staithe 2 | 03/2009 | ||
| Hoveton Viaduct | Delayed | ||
| Commissioners Cut | Completed | ||
| Hoveton BIC | Delayed | ||
| Woodbastwick | Delayed | ||
| Ranworth | Completed | ||
| Rockland | 03/2009 | ||
| Geldeston | 03/2009 | ||
| Weed control | Various locations | Completed | |
| Signage | Various locations | Speed, direction & information | Ongoing |
| Litter | Various locations | Ongoing | |
| Installation/recovery navigation bouys | Various locations | Completed | |
| Various locations | Completed | ||
| Weed cutting | Somerton 1 | Completed | |
| Somerton 2 | Completed | ||
| Martham Dyke | Completed | ||
| Horsey/Waxham | Completed | ||
| River Bure | Completed | ||
| Norwich | Completed | ||
| Whitlingham Great Broad | (Contracted) | Completed | |
| Geldeston | 08/2008 | ||
| Removal of dangerous overhanging trees | Reactive | Ongoing | |
| Winter tree work | Wroxham Bridge - Coltishall | 11/2008 - 02/2009 | |
| River Ant (Upper Reaches) | 11/2008 - 12/2008 | ||
| Removal of navigation obstructions | Reactive | Ongoing | |
| Removal of fish barriers | Barton Broad | 05/2008 | |
| Emergency/reactive repairs | Ludham Bridge Footpath | Completed | |